Data center sustainability in a colocation contract comes down to five written commitments: PUE measured to ISO/IEC 30134-2, water use (WUE), power sourcing reported on both location-based and market-based terms, access to meter data, and the provider’s own EU or national reporting status. Ask for them before you sign, not when the auditor asks.
Your servers may sit in someone else’s building, but the electricity they draw still lands in your sustainability report. For a utility, that report faces regulators, investors and customers who expect you to hold your own IT to the standard you ask of others. The numbers behind it are rising fast: Berkeley Lab estimates that US data centers used about 176 TWh in 2023, or 4.4% of US electricity, and projects 325 to 580 TWh, or 6.7% to 12%, by 2028.
Why does a colocation contract decide your footprint?
A colocation provider controls the building, the cooling and the power contract. You control only the IT load. That split means the provider holds most of the data you need, and you hold the obligation to report it.
Where your colocated load sits in your own inventory depends on how you set your organizational boundary and on the lease terms. Under some boundaries it falls in Scope 2, under others in Scope 3. Settle that with your GHG accounting lead before you write the questions below, because the answer decides which figures you need and how precise they must be.
For scale, the EU reporting threshold discussed below is 500 kW of IT load, and a single 1 MW deployment at PUE 1.5 draws about 13,140 MWh a year (1.5 x 8,760 hours).
The practical rule: any number you will publish must be a number the provider has agreed to give you, in writing, on a schedule that matches your reporting calendar.
Which metrics should a provider hand you?
Start with the efficiency and resource metrics the industry has standardized. ISO/IEC 30134-2 defines how to measure, calculate and report Power Usage Effectiveness (PUE); its second edition was published in January 2026. ISO/IEC 30134-9 does the same for Water Usage Effectiveness (WUE). Fruggr’s GreenOps primer also covers carbon usage effectiveness (CUE) and energy reuse factor (ERF).
| Metric | What it tells you | What to ask the provider |
|---|---|---|
| PUE | Facility energy divided by IT energy | Measured to ISO/IEC 30134-2? Which measurement category? Annual or trailing 12 months? |
| WUE | Water used per unit of IT energy | Which cooling type? Where does the water come from? |
| CUE | Carbon emitted per unit of IT energy | Computed with location-based or market-based factors? |
| ERF | Share of energy reused outside the facility | Is waste heat exported, and to whom? |
| Renewable share | Share of supply covered by renewables | Contracted how, and matched annually or hourly? |
Efficiency gains have also stalled. A trade-press summary of the Uptime Institute’s 2025 survey reports a global average PUE of 1.54, flat for the sixth consecutive year, and Uptime itself says average PUE has shown little change for six years. A provider quoting a design PUE well below that average deserves a request for measured, metered data.
How much does a PUE gap cost you?
PUE sounds abstract until you apply it to a real load. Take a 1 MW IT deployment running all year (8,760 hours):
- At PUE 1.3, the facility draws 11,388 MWh a year.
- At PUE 1.6, it draws 14,016 MWh a year.
- The difference is 2,628 MWh a year for the same compute.
At an assumed $80 per MWh (an illustration, not a quote), that gap is about $210,000 a year. Multiply 2,628 MWh by your own grid or contract emission factor and you have the carbon difference. The gap shows up in your electricity pass-through, your Scope 2 or Scope 3 figure, or both.
What should you ask about power and carbon?
Carbon claims are where colocation proposals get vague. Ask for two figures, not one: emissions calculated with the location-based method (the grid’s average mix) and with the market-based method (the provider’s contracts and certificates). The GHG Protocol’s Scope 2 Guidance sets eight quality criteria for the contractual instruments behind a market-based figure, so ask which instruments the provider uses and whether they meet those criteria.
Then press on three details:
- Contract type: a power purchase agreement tied to new generation, or unbundled certificates bought after the fact.
- Matching: annual totals or hourly. Annual matching can report near-zero market-based emissions for a facility that runs on grid power at night.
- Change notice: how much warning you get if the sourcing mix changes mid-contract.
What should you ask about water and cooling?
Low PUE can come with high water use, because evaporative cooling cuts electricity at the cost of water. That is why WUE belongs next to PUE in every proposal, reported at the same monthly frequency; ISO/IEC 30134-9, published in 2022, gives you the definition to cite. Ask for the cooling design (air, evaporative, liquid), the water source, and whether the site sits in a water-stressed basin. A utility that runs hydro, thermal or nuclear assets already knows how local water limits constrain operations; apply the same question to your IT footprint.
What does EU reporting give you, and what does it not?
If any of your colocation sites are in the EU, the provider may already be reporting. Delegated Regulation (EU) 2024/1364 requires operators of data centres with an IT energy demand of at least 500 kW to report 24 performance indicators to the European database, with deadlines of 15 September 2024, 15 May 2025 and annually after that (verify current text with counsel).
The catch for buyers: the data is published in aggregated form at Member State and EU level, and Member States must keep the underlying information confidential as business secrets. You cannot look up a specific facility. You have to ask the provider for its figures and write the right to receive them into the contract.
What does this mean in the US and Canada?
The load-growth numbers above come from the US Department of Energy and Berkeley Lab, and they matter twice for a utility: as a buyer of colocation space and as the supplier whose grid serves it. We did not find a US federal counterpart to the EU reporting scheme, so for North American sites the contract is your main source of data (verify current federal, state and provincial rules before relying on this). If you report under CSRD, a Canadian sustainability standard or a US state climate rule, the same questions apply: metered energy, water, and carbon on both methods, delivered on your reporting calendar.
Which contract clauses make the answers enforceable?
Answers in a sales call are not evidence. Put these terms in the master services agreement or its schedules:
- Metered data: monthly facility and IT energy readings, with the PUE measurement boundary written out.
- Audit right: the ability to verify meter data and certificate retirement once a year.
- Reporting calendar: figures delivered at least 30 days before your own reporting deadline.
- Water and carbon: WUE and both carbon figures delivered with the energy data.
- Change notice: written notice of any change in power sourcing or cooling design.
What can you do this quarter?
- List every colocation contract and tag each by country, IT load in kW and who holds operational control.
- Send the same ten-line questionnaire (PUE, WUE, CUE, renewable share, matching, cooling, reporting status, audit right) to every provider.
- Compare answers in one table and flag any provider that cannot give metered PUE or both carbon figures.
- Rank sites by IT load; start contract renegotiation with the largest loads first.
- Feed the verified numbers into your ESG data pipeline, and keep a note of what each provider declined to share.
If cloud workloads sit alongside colocation, the same usage data supports cost and carbon together; see how FinOps and GreenOps combine them.

Key takeaways
- Provider data is your data: colocation puts your electricity in someone else’s meter, so the contract must guarantee the readings you will publish.
- Ask for PUE to ISO/IEC 30134-2 and WUE to ISO/IEC 30134-9, plus carbon on both the location-based and market-based methods.
- EU reporting under Regulation 2024/1364 is aggregated and confidential, so write data delivery and audit rights into the contract instead of relying on public data.
Next step: See how Fruggr ESG IT reporting collects cloud, data center and workstation data for sustainability reporting.
FAQ
Data center sustainability is the practice of measuring and reducing a facility’s energy, water and carbon impact, using metrics such as PUE, WUE, CUE and the share of renewable energy.
There is no single threshold, but the 2025 Uptime Institute survey, as summarized by trade press, reports a global average of 1.54. Ask for metered PUE to ISO/IEC 30134-2 and compare it with that average.
No. PUE measures energy efficiency only. A facility can have a low PUE and high water use, or a low PUE and a carbon-heavy power mix, so check WUE and carbon too.
Under Delegated Regulation (EU) 2024/1364, operators of data centres with an IT energy demand of at least 500 kW report to the European database. Verify current text with counsel.
It depends on your organizational boundary and lease terms, and can fall in Scope 2 or Scope 3. Confirm with your GHG accounting lead.